Big Pit is a real coal mine and one of Britain’s leading mining museums

Big Pit is a real coal mine and one of Britain’s leading mining museums

Client: Big Pit
Region: UK
Industry: Coal Mine
Big Pit SDS Case study
“Attention to detail and technical expertise readily available”

“Great company to work with, efficient and professional in their approach. Attention to detail and technical expertise readily available to complete the job to a high standard, would highly recommend!”

Dwaine Smith
Big Pit Electrical Engineer

The Situation

Situation

A relationship that has spanned over 5 years, SDS have supported Big Pit National Coal Museum with parts and engineering consultation since 2017. Located in Blaenavon, South Wales, Big Pit is one of Britain’s leading mining museums. As part of the experience, guests can travel 300ft below ground using the specially designed winder system that allows the cages to travel the shaft.

Once underground the quests are given an exclusive tour by an ex-miner where they navigate the old roadways and gaining an appreciation for life as a collier in coal mining. Our most recent project for the National Coal Museum involved supporting this very system.
Challenges

Even though Big Pit is no longer a working coal mine it still comes under the current mining regulations and is governed by the mine’s inspectorate. The system that we developed had to be fit for purpose, meet the current safety requirements for man riding and conform to all current standard regulations.

The museum is operational 7 days a week, 362 days a year so we had an allocated timeframe, with a challenging environment to contend with.
Vina Panchal Rishi Panchal

The Solution

The drive control that operates the winder that lowers the cage needed updating as parts were now obsolete and the ever-growing need for energy efficient systems. The client required a system that was fit for purpose: to support the weight of the visitors and lower them at a set speed into the coal mine. The technology they used prior to our visit was becoming obsolete and spare parts were becoming difficult to source. Having been in place since 1952, hence why the system required review and modernising.

Benefits

Energy Efficient
The new system is energy efficient because of the AFE, it will also allow Big Pit to generate income from the excess energy produced from each wind.
Maintain Authenticity
The original controls were retained to keep the authenticity of a coal mining winder system – even though we are updating the system, we are retaining the same control features – so the classical feature (Operated with 2 drive’ levers) can still operate the winder.
Accurate Distance
By adding an HMI screen, the operator can observe where the cages are in relation to the shaft at a much more accurate distance to conform to current requirements and regulations.

Ready to solve your own manufacturing challenges?

Unlock 5% off your first order when you sign up!

By submitting this form, you consent to being contacted in alignment with our privacy policy.

  • This field is for validation purposes and should be left unchanged.
Keep in the Know!

We know everyone, everywhere wants your details. The reason why we would like them is this: we want to serve you better by creating information that’s useful to you whilst stocking products you want to buy.

  • This field is for validation purposes and should be left unchanged.
Join 12,973 engineers who love our news & updates.

If you are kind enough to trust us with your information, we promise to keep you updated with useful information and not to share your details with anyone else.

  • This field is for validation purposes and should be left unchanged.